Where changes come from
- Owner requests: a different finish, an extra room, a new layout.
- Design errors and omissions found during construction, often through a request for information.
- Site conditions nobody could see at tender, such as rock or buried services.
- Authority requirements that change after the design was approved.
- Value engineering: a cheaper or faster alternative the contractor proposes.
From a field change to a signed order
- Record the change event when it happens: who instructed it, what, where, with photos.
- Price it: labour, materials, equipment, subcontractor quotes, overhead and margin as the contract allows, and the effect on the schedule.
- Submit the change order request with the backup.
- Negotiate and agree, or record the disagreement in writing.
- Sign it, then update the contract value, the budget and the schedule.
Some contracts let the owner instruct the work before the price is agreed. In the AIA contract documents common in the United States this is a construction change directive: the work goes ahead and the valuation follows.
Why records settle disputes
Most change disputes come down to proof: who instructed the change, when, and what it really cost. Imagine a subcontractor told by a site engineer to move the openings in a wall. The work is done, nobody signs anything, and months later the payment is contested. A daily record with the instruction, photos and hours would have turned an argument into a review. Many contracts also require written notice within a set time after the event, and a late notice can weaken or lose the claim, so check the contract with your contract manager or counsel. This example is hypothetical.
What a change order log should show
Each change needs a number, a status (identified, priced, submitted, approved or rejected), its value, its time impact and links to the RFIs, drawings and photos behind it. Reports should keep approved changes apart from pending ones, so the revised contract value is real and the pending exposure is visible. That is the core of change order management software, fed by site progress reporting.