What a good RFI contains
- A number, a short subject and one question. Two questions in one RFI tend to get half an answer.
- Exact references: drawing number and detail, specification section, and the location on site, such as grid line and level.
- A proposed solution where the contractor has one. It is often the fastest route to an answer.
- The date a response is needed and the work it is holding up.
- Who it is addressed to, who receives copies, and photos or marked-up drawings.
The path from site to answer
A site engineer or subcontractor raises the question. The general contractor checks it first, to weed out duplicates and questions the documents already answer, then sends it to the architect or engineer; on many Gulf projects that is the supervising consultant. At each step one party holds the ball in court: the one who must act next. When the answer arrives it goes to everyone affected, the drawings are updated, and if it changes scope, cost or time it leads to a change order.
Why the log matters
Imagine a fit-out contractor who finds that the ceiling height on the architectural drawings leaves no room for the duct on the mechanical drawings. The RFI goes out with both drawing references and a proposed fix. If the answer takes three weeks, the ceiling crew stands idle, and the RFI log is the record of when the question was asked and when it was answered. In a later delay claim, that record counts for more than anyone's memory. This example is hypothetical.
Habits that slow projects
- Vague RFIs that say please advise, with no references.
- Using an RFI to ask for a change, which belongs in a change request.
- Settling a question in a site conversation, in Arabic or English, and never issuing the written RFI.
- Nobody watching due dates, so overdue RFIs surface only at the progress meeting.
Not the procurement RFI
In purchasing, RFI means something else: an early request to suppliers for general information, before a request for quotation or proposal. That process belongs with procurement quote comparison. For tracking construction RFIs alongside submittals, see RFI and submittal tracking.